Answer:
d. It determines the critical path for the completion of a series of interrelated activities.
Explanation:
The Critical Path method is a method to lay out the different steps or interrelated activities of a project, in a graphical manner, that shows the interrelations, the time each activity takes to complete, the different alternatives or paths for project completion, and the total completion time for the project.
It also shows the amount of time a delay in one of the activities would delay the project as a whole.
Answer:
b. $18,000
Explanation:
The computation of outstanding checks is shown below:-
Outstanding checks as of the end of July = Start with outstanding checks as of June + Amount of checks issued in July - Amount of checks that cleared in July
= $5,400 + $38,900 - $26,300
= $44,300 - $26,300
= $18,000
Note, The $300 check was issued by a customer, not Darlene.
So, for computing the outstanding checks as of the end of July we simply applied the above formula.
Answer:
12%
Explanation:
Annual net income:
= Increase in annual revenue - Increase in annual costs
= $220,000 - $160,000
= $60,000
Average investment:
= (Initial investment + Salvage value at the end) ÷ 2
= (980,000 + 20,000) ÷ 2
= $500,000
Annual rate of return:
= (Annual net income ÷ Average investment) × 100
= ($60,000 ÷ $500,000) × 100
= 12%
Answer:
The correct answer is binary variables.
Explanation:
A binary variable is one that can only have two possible values. They generally fulfill two essential characteristics:
1. They are made up of two exhausting values, which indicates that there is no other possibility of response. For example, a person is female or male.
2. Both values of the variable are exclusive, that is, it is not possible that both responses can be given, only one. In the same example above, a customer cannot be a woman and a man at the same time.
Answer:
false
Explanation:
he/she is not allowed to enter at any time because he/she does not have the right to enter the home if you are not there.