On average, the project takes 4 weeks to complete.
Step-by-step explanation:
We have these following probabilities:
25% probability that the activity takes 2 weeks.
50% probability that the activity takes 4 weeks.
25% probability that the activity takes 6 weeks.
How long does the project now take to complete (on average)
We multiply each duration by it's probability.
0.25*2 + 0.5*4 + 0.25*6 = 4
On average, the project takes 4 weeks to complete.
Answer: A
Step-by-step explanation:
This is the concept of algebra, given that ab^4=12 and a^5b^5=7776, the value if a will be found as follows:
ab^4=12
a=12/b^4
also;
a^5=7776/b^5
thus;
a=(7776/b^5)^(1/5)
a=6/b
thus the value of a will be:
6/b=12/b^4
dividing both sides by b we get:
6=12/b^3
multiplying both sides by b^3 we get
6b^3=12
b^3=2
hence;
b=2^(1/3)
f(x) = 2x
g(x) = x + 3
First let us find (fog)(x)
<span />
(fog)(x) = f(g(x)
= f(x+3)
= 2(x+3)
= 2x + 6
==> (fog)(x) = 2x + 6
Now let us find (gof)(x):
(gof)(x) = g(f(x)
= g(2x)
= 2x + 3
==> <span>(gof)(x) = 2x + 3</span>
Answer:
Approximate of error = 11.11 % (Approx.)
Step-by-step explanation:
Given:
Exact value = 50
Approximate value = 45
Find:
Approximate of error
Computation:
Approximate of error = [(Exact value - Approximate value)/Approximate value]100
Approximate of error = [(50 - 45)/45]100
Approximate of error = [(5)/45]100
Approximate of error = [0.11111]100
Approximate of error = 11.11 % (Approx.)