<span>Vinny might be able to force the completion of the project. If the two had a written agreement that has not been violated or made conditionally null, then Spud could be legally obligated to complete the project, dependent on the interpretation of the contract by the court.</span>
Answer:
$0
Explanation:
The computation of the annual amortization for goodwill is shown below:
As we know in the case of goodwill, the impairment test is to be done on periodic basis and if there is any fall in the value so the same is to be reported as the impairment loss
So for goodwill, no amortization is to be done
hence, the annual amortization is zero
Answer:
Explanation:
WORK IN PROCESS INVENTORY
May 1 balance 3770 May 31 Finished Goods 9234
31-May Material 11470
31-May labour 13870
31-May Overheads 9431.6
may 31 Balance 29307.6
JOB COST SHEET
Job no. Beg. WIP Material Labour Overheads Total
430 1340 3850 3400 2312 10902
431 0 4680 8170 5555.6 18405.6
TOTAL 1340 8530 11570 7867.6 29307.6
Note: Total cost of Job 429 transferred to Finished goods:
Beginning cost 2430
Add: Material 2940
Add: Labour 2300
Add: Overheads (2300*68%) 1564
Total cost of Job 429 9234
Answer:
The cost assigned to Job 7 at the end of the week is 5,700 dollars.
Explanation:
In job order costing the cost that is to be assign to a specific order is sum of actual direct material cost and actual labour cost require to perform that job. Factory overheads are also added to the job cost on the basis of allocation method (on basis of budgeted applied OH rate).
So Following costs will be assign to Job 7.
RAW materail = $ 700
Labor Cost = $ 3000
Overhead = $ 2000 (10* 20)
Total Cost = $ 5700