Answer:
0.726 is the probability that the project will be completed in 33 days or less.
Step-by-step explanation:
We are given the following information in the question:
Mean, μ = 30 days
Variance = 25 days
Standard Deviation,

We assume that the distribution of path length is a bell shaped distribution that is a normal distribution.
Formula:

P(completed in 33 days or less)
Calculation the value from standard normal z table, we have,

0.726 is the probability that the project will be completed in 33 days or less.
Answer:
y=1/5x+11/5
Step-by-step explanation:
Find the slope of the original line and use the point-slope formula y-y^1=m(x-x^1) to find line parallel to -x+5y=1
Hope this helps
The results of the arithmetic evaluations as given in the task content are; 40,42 and 62.
<h3>What are the results of the arithmetic evaluations?</h3>
The arithmetic operations above can be evaluated and simplified as follows;
(11-8)x3+7+27-3 = (3×3)+7+27-3 = 40.
(18÷3)+6+(14-8)x5 = (6)+6+(6)x5 = 42.
(11-7)x6+4+32-4 = (5×6) +4 +32-4 = 62.
Read more on arithmetic evaluations;
brainly.com/question/4694189
#SPJ1
Answer:
8 cm
Step-by-step explanation:
100% sure