Answer:
$28,000 Underapplied
Explanation:
Calculation for what the balance in the Factory Overhead account is
Estimated Overhead Cost/Estimated DL = Overhead Rate
$432,000/$2,160,000 = 20 %
Actual Overhead: $404,000
Applied Overhead: (DL 20%) = ($1,880,000 20%) = $376,000
Actual OH - Applied OH = FOH
$404,000 - $376,000 =
$28,000 Underapplied
Therefore At year-end, the balance in the Factory Overhead account is a:$28,000 Underapplied
Answer:
Answer for the question:
A company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below:
Immediate
Activity
Designation
Predecessor
Time in Days
Break down both machines
A
None
3
Clean machine 1
B
A
3
Clean machine 2
C
A
3
Re-set machine 1
D
B
1
Re-set machine 2
E
C
2
Re-calibrate both machines
F
D and E
1
Final test
G
F
2
Using the Single Time Estimate CPM procedure, what is the critical path for the project & the overall project duration?
e. ABCDG & 10 days
c. ABDFG & 10 days
d. ABDFG & 11 days
b. ACEFG & 10 days
a. ACEFG & 11 days
is given in the attachment.
Explanation:
Having a good attitude towards work.
Never look at what you can not do, try to see what your good at.
Having good communication with the people you work with.
What should be the basic goal of a firm when it sets a level of output?
The firm should make sure that it maximizes its profits. Maximizing profits means they are making the most they possibly can with the items they are selling or services that are being offered. When they make their overall goals, they need to make sure they are going to be making as much as they possibly can to acheive their long-term goals.
Answer:
b. Hiring other firms to do the work
Explanation:
Subcontracting is the practice of hiring or outsourcing, part of the obligations , duties and work under a contract to another firm. this firm is known as a subcontractor