Answer:
2 for graph 1/2 for equation
Step-by-step explanation:
the rate of change is just another word for slope
using the equation rise/run the slope is 2/1 for the graph
but tin the equation the rate of change is 1/2
(the function is not equal to the graph.)
Answer:
1.07
Step-by-step explanation:
1 To convert to a decimal, divide the percent number by 100.
<h3>107÷100=1.07</h3>
2 Therefore, the decimal form is 1.07
<h3>1.07</h3>
Answer:
B, 224in2
It may get tedious but just find the area of each face and write them down
Step-by-step explanation:
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.