Answer:
Applet's flexible budget variance for total costs is $5,140 unfavorable variance since actual is higher than budgeted cost
Explanation:
Flexible budget variance for total costs=actual total costs-budgeted total costs of 72 connectors
actual total costs of 72 connectors=$19,000
budgeted total costs of 72 connectors=budgeted fixed cost+budgeted total variable cost of 72 connectors
total budgeted variable cost=72*$130=$ 9,360.00
budgeted fixed cost is $4,500
Budgeted total costs of 72 connectors=$9,360.00+$4,500.00=$ 13,860.00
Flexible budget variance =$ 13,860.00-$19,000.00=$5140 unfavorable variance
Answer:
the first option is the correct one
Answer: Document the risk and calculate the expected monetary value based on the probability and impact of the occurrences.
Explanation:
Risk response refers to the development of strategic options to reduce the threats and enhance opportunities to the objectives of the project.
It should be noted that when new risks are identified, such risks go through the process of risk management and one needs to be able to know the risk probability and risk impact and then get to curtail them.
Answer:
Hi, I found a gift hope u like it
Explanation:
IT'S ON AMAZON
Answer:
a. The lead time
Explanation:
The lead time is the time that shows the difference between the time at which the process gets started and the time at which the process get finished. This can be reviewed in the manufacturing, supply chain management at the time when there is a prior processing, within processing and after processing
Therefore according to the given situation, the option a is correct
hence, all the other options are incorrect
=