Answer:
$14,000 under applied
Explanation:
Given that
Material production = $203,000
Application rate = 150%
The computation of amount of overhead is shown below:-
Overhead = Material production × Application rate
= $203,000 - ($126,000 × 1.5)
= $203,000 - $189,000
= $14,000 under applied
Therefore, for computing the overhead we simply multiply the material production with application rate percentage.
The amount of interest to be paid in total for six and a half years is $59,357.31
Computation:
Given,
Principal Amount =$44,500
Interest rate =13.11% annually
The interest is compounded monthly
time period= 6.5 years
The formula of compound interest will be used:
Substituting the values in the formula:
Now, the value of total interest paid is computed by taking the difference between the annuity amount and the principal amount.
Therefore, from the given options non of the options are correct.
To know more about compound interest, refer to the link:
brainly.com/question/25857212
Answer:
the minimum point on the AVC curve
Explanation:
The average variable cost denoted as AVC represent all the variable costs as electricty, water, gas, etc. divided by the output produced.
Where VC is the variable cost and Q represent the output produced.
In the short-run, a firm can "increase profits if the marginal revenue obtained from selling a product if exceeds the marginal cost of making that product".
And the lowest point on a competitive firm short run needs to correspond to the minimum point on the AVC curve since we assume that we are in a competitive firm's scenario, all the prices and variable costs needs to be as lowest possible in order to be competitive.
Answer:
Total direct labor variance= $960 favorable
Explanation:
Giving the following information:
We will separate the direct labor cost variance in rate and quantity variance. <u>To calculate the direct labor rate and quantity variance, we need to use the following formulas:</u>
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Direct labor time (efficiency) variance= (30*6 - 130)*14
Direct labor time (efficiency) variance= $700 favorable
Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity
Direct labor rate variance= (14 - 12)*130
Direct labor rate variance= $260 favorable
Actual rate= 1,560/130= $12
Total direct labor variance= 700 + 260
Total direct labor variance= $960 favorable
Answer:
Total Assets=$13,500
Explanation:
Assets are items which are used by any company or firm for positive economic value production.
In our problem, we have to find total assets.
Given Data:
Accounts Receivable=$800
Equipment=$10,000
Accounts Payable=$4,200
Prepaid Rent=$2,000
Supplies=$400
Bank Loan=$1,600
Tools= $300
Total Assets=Accounts Receivable+Equipment+Prepaid Rent+Supplies+ Tools
Total Assets=$800+$10,000+$2,000+$400+$300
Total Assets=$13,500