Answer:
Direct material price variance= $12,500 unfavorable
Explanation:
Giving the following formula:
The standard price per pound is $2.00.
The actual quantity of materials purchased and used in production is 50,000 pounds.
The actual purchase price per pound of materials was $2.25.
<u>To calculate the direct material price (spending) variance, we need to use the following formula:</u>
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (2 - 2.25)*50,000
Direct material price variance= $12,500 unfavorable
Answer:
a. Advertising costs relative to the number of customers for a particular restaurant. [Fixed]
b. Rental costs relative to the number of restaurants. [Variable]
c. Cooks salaries at a particular location relative to the number of customers. [Fixed]
d. Cost of supplies (cups, plates, spoons, etc.) relative to the number of customers. [Variable]
e. Manager's compensation relative to the number of customers. [Mixed]
f. Servers' salaries relative to the number of restaurants. [Variable]
Explanation:
Huey Long guaranteed a free training through school and benefits for the matured, which he can't do on the grounds that it is the administration's business to settle on these choices. He likewise he raised duties to make healing facilities to take into account poor people and enhance ignored streets and scaffolds inside the state
Answer:
B
Explanation:
Reserves J: Excess reserves J: Loans J: Deposits ;Money supply
Answer:
See below
Explanation:
The below shows the calculation of variance
Budgeted direct labor (per unit) 0.60
Units 2,000
Budgeted direct total labor (hrs) 1,200
Actual hours 1,160
Standard rate $17
Direct labor efficiency variance
The direct labor efficiency variance
= (Budgeted hours - Actual hours) × Standard rate
= (1,200 - 1,160) × $18