Answer:
Direct labor time (efficiency) variance= $3,000 favorable
Explanation:
Giving the following information:
Standard= 2 hours of labor per unit, at $12 per hour.
In producing 3800 units, Waterway used 7350 hours of labor.
<u>To calculate the direct labor quantity variance, we need to use the following formula:</u>
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
Standard quantity= 2*3,800= 7,600 hours
Direct labor time (efficiency) variance= (7,600 - 7,350)*12
Direct labor time (efficiency) variance= $3,000 favorable