Answer:
225,000 shares
Explanation:
A company's shares outstanding refers to the total number of shares investors currently own.
Beck Corp. issued 200,000 shares of common stock when it began operations in year 1 and issued an additional 100,000 shares in year 2.
In year 3, Beck purchased 75,000 shares of its common stock and held it in Treasury.
At December 31, year 3, the number of shares of Beck's common stock were outstanding is
200,000 shares in year 1
100,000 shares in year 2
Total Common Stock = 300,000
less: Treasury Stock of 75,000
Outstanding Stock = 225,000 shares
~Hello There!~
I'd say it is Electing a board of directors.
Hope This Helps You!
Good Luck :)
Have A Great Day ^_^
- Hannah ❤
Answer: Option (B)
Explanation:
Condition subsequent clause is referred to as an exit clause from the existing contract. This agreement in between the parties tends to include languages that loosens or frees one of individuals from the agreement or the deal. This tends to mostly occur when the conditional outcome or result takes place. The conditional subsequent relieves an individual or a party from all the obligations.
Answer:
The correct answer is (B) Buy euro at $1.50/€, buy £ at €1.25/£, sell £ at $2/£
Explanation:
The dollar- euro exchange rate is quoted as $1.50 = €1.00
the dollar-pound exchange rate is quoted at $2.00 = £1.00
To calculate the actual cross rate we use; S(euro divided by pounds) = S(dollar/pounds) ÷ S(dollar/euro).
Using symbols to denote this, we have S(€/£) = S($/£) / S($/€)
S(€/£) = S(2/1) ÷ S(1.50/1)
= (2 / 1.5)
= €1.33.
Consequently, from this result we now know that the euro is undervalued with respect to pounds under the cross rate being offered by the bank. This implies that you should first buy the euro, convert to pounds, and eventually convert back to dollars, this would enable you make money as an investor.
Answer: c. 5 days, 7 workers
Explanation: With the project requirements provided, and with the least of number of resources working on the task not less than the number of those assigned to the task.
The least amount of time for the project to complete would be approximately 5 days, and the resources needed to complete the task would be approximately 7 workers.