Answer:
2 workers = 6 days
4 workers = 3 days
Step-by-step explanation:
If it takes 2 workers 6 days, if you seep up the process with 4 workers, you would divide the days by 2 because you multilpied the workers by 2. So, it would take 3 days with 4 workers. I hope that makes sence.
Answer:
5 and 4
Step-by-step explanation:
So if, x equals 2 then all you do is turn the x into a 2.
So you rewrite the equation into,
2 + 3 and 2 x 2,
Which would be 5 and 4
Hope this helps!
Answer:
HJ = 8 JE = 4
Step-by-step explanation:
it is given that H is the midpoint of GE and J is the midpoint of FE. According to the midpoint theorem the line segment connecting the midpoint of two sides is parallel to the three side and its length is half of the third side. since JH is connecting the midpoints.
HJ= 1/2 (GF)
x + 3 = 1/2 (4x - 4)
x + 3 = 2x - 2
x = 5
^ Thus meaning the value of x is 5.
Now you just fill into your equations:
HJ = x + 3 = (5) + 3 = 8
JE = x - 1 = (5) - 1 = 4
Therefore, HJ = 8; JE = 4.
1)We need to know the amount of yellow tint in the old mixture.
amount of yellow tint=30% of 40 liters
30%=30/100=0.3
Amount of yellow tint=0.3(40 liters)=12 liters.
2)We need to find the amount of yellow tint in the new mixture.
amount of yellow tint in the new mixture=12 liters + 9 liters=21 liters.
3) we calculate the amount of the new mixture:
amount of new mixture=40 liters + 9 liters=49 liters
4) we compute the percent of yellow tint in the new mixture:
percent of yellow tint =(amount of yellow tint / amount of mixture)*100
percent of yellow tint=(21 liters / 49 liters)100≈42.9%
Answer: The percent of yellow tint in the new mixture is 42.9%.
note: if this answer is not correct you can try it with 42.8%
If x orignial price than 60/100*x=80/100*(x-40) and selling price =60/100*x=96