Answer:
True
Explanation:
Critical-Chain
This was introduced or originated by Eli Goldratt in 1997. Its aim is to challenges conventional project management approaches and absolute dependence on TOC principles. The idea of what to change or eliminated is the largely rooted behaviors that is common with the traditional project management practices. It is very multitasking anf it is the longest string of reliance that occur on the project.
Critical- Chain Approach
This approach simply covers project network as it ca be limited by both resource and technical reliance/dependencies. each type of limitations can create task reliance.
The Summary of Critical Chain Approach
1.) use Aggressive but Possible Times (ABPT) for task durations
2.) identify the critical chain by accounting for resource dependencies
3.) use buffer management to track project progress etc.
Answer:
See below
Explanation:
The below shows the calculation of variance
Budgeted direct labor (per unit) 0.60
Units 2,000
Budgeted direct total labor (hrs) 1,200
Actual hours 1,160
Standard rate $17
Direct labor efficiency variance
The direct labor efficiency variance
= (Budgeted hours - Actual hours) × Standard rate
= (1,200 - 1,160) × $18
= $720 favourable
Answer:
- Melba's adjusted basis for the land at the Acquisition date is $625000
- Melba's adjusted basis for the land one year later is $645000
Explanation:
The adjusted basis for a property/land is the net cost of the property after adjusting for factors that might attract tax as related to the land
The adjusted basis for the land at the acquisition date is the net cost of the land at the acquisition date which will be ( $225000 + $400000 ) because that was the net cost of the Land at the date of acquisition before an agreement was later reached by Melba requiring him to pay $400000 plus an interest of 5%
Hence the adjusted basis for the land one year later will be
= ( $225000 + $400000 ) + 5% of $400000
= ( $625000 ) + $20000
= $645000
The project's projected NPV is $185.11. (second option)
<h3>What is the NPV?</h3>
Net present value is the present value of after-tax cash flows from an investment less the amount invested. Only projects with a positive NPV should be accepted.
A project with a negative NPV should not be chosen because it isn't profitable. NPV is calculated by taking the present value of all cash flows over the life of a project. Then, the present value of cash flows is subtracted from the investment's initial investment
NPV = -1200 + 400 / 1.0975 + 425 / 1.0975² + 450 / 1.0975³ + 475 / 1.0975^4
= $185.11
To learn more about net present value, please check: brainly.com/question/25748668
#SPJ1