Answer:
Optimistic duration
Explanation:
The following three concepts are Project management concepts:
Optismitic duration: Estimation of the shortest duration of a task, taking into account the difficulty, etc.
Pessimistic duration: Estamation of the longest duration of a task, taking into account the difficulty, etc
Expected duration: Expected duration of a task, kind of a compromise between the optmistic duration and the pessimistic duration.
Which of the following is the estimate of the minimum amount of time it would take to perform a task?
The answer is Optimistic duration
Answer:
To get the IP address and other information on the workstation, type 'ipconfig' for windows or 'ifconfig' or Linux and press the return key.
The subnet mask is a class B type and 169.254.14.11 IP address shows that the workstation cannot access the DHCP server, so the IP address is not properly configured for network connection.
Explanation:
A computer network is an interconnection and intercommunication of two or more computer devices. All devices in a network must have an IP address, which can be static or dynamic from a DHCP server.
When a computer is configured to receive IP address from a DHCP server, but cannot reach the server, the IP address from the range of 169 is automatically assigned to it but still would not be able to communicate with other devices in the network.
I don’t know if this helps, but here are three types of main flows: flow of material/goods, flow of money/cash, and flow of information.
Refer to the attachment!!