Answer: 2.77
Explanation:
Portfolio Beta is the Weighted Average Beta of all the individual stocks in a portfolio.
Seeing as the other betas and proportions are given, we can plug this into a formula to find out the beta of stock B.
In case you do not see a beta for the U.S. Treasury bills that's fine because beta is a measure of risk and U.S. Treasury bills have NONE so that means that their better is 0.
And if you are wondering what the beta of stock A is, the answer is 1 because that is the beta of the overall market by definition.
Creating a formula therefore we have,
1.75 = 0.17(0) + 0.31(1) + 0.52x
0.52x = 1.75 - 0.31
0.52x = 1.44
x = 2.76923076923
x = 2.77 (2dp)
2.77 is the beta of Stock B.
Answer:
Instructions are below.
Explanation:
Giving the following information:
Total fixed costs= 300,000
Total costs= $450,000
Units= 120,000
A) Unitary variable cost= 150,000/120,000= $1.25
B) Units= 75,000
<u>The fixed costs remain constant no matter how many units are made (between relevant ranges).</u>
Total fixed costs= $300,000
C) UNits= 160,000
Total variable costs= 1.25*160,000= $200,000
D) Units= 180,000
Total fixed costs= 300,000
Total variable costs= 1.25*180,0000= 225,000
Total costs= $525,000
Geochemist is the answer your looking for
Answer:
P = $75 per club
n= 75,000 clubs
Explanation:
The demand and supply functions are:

The equilibrium price is the price that yields a quantity demanded equal to the quantity supplied:

The number of units sold at that price is:

Answer:
<u>Establish project priorities</u>
Explanation:
<em>Remember</em>, we are told the project professional has been assigned to manage a project, therefore going by the guiding steps when defining a project, the next and second step he should take is to establish project priorities.
In other words, he should draft out what tasks should be done first, those for later, and so forth in other to successfully achieve/finish the project's objective.