Answer:
$3443.86
Explanation:
a=p(1+r/n)^nt
a=2450(1+.0525/12)^12*6.5
3443.86
Answer:
A) Year 1 cost of goods sold
B) Year 2 cost of goods sold
D) Year 2 beginning inventory
Explanation:
A) Year 1 expense of merchandise sold : The Current year cost of Goods Sold is processed by deducting finishing stock from Opening Inventory and Purchases made during the year. So in the event that the completion stock isn't right, at that point the result of above calculation will not be right so the Year 1 expense of merchandise sold for example (Current year cost of Goods Sold) will be inaccurate.
D) Year 2 starting stock: year 2 starting stock is equivalent to year 1 completion stock. So on the off chance that off-base stock estimation is made at end of earlier year, at that point current year opening worth will be carried on as off-base.
B) Year 2 expense of merchandise sold: The explanation is same as ans q(i.e. Year 1 expense of merchandise sold) as off-base convey forward opening stock worth will bring about wrong calculation of cost of products sold for year 2.
<span>Both of these examples are illustrative of the "behavior" element of the assertive message format. These example are objective in that they only outlined what happened in a given situation. Although the second may appear to have an emotional connotation, it simply gives an objective impression of what happened.</span>
Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.