Formatted based on the source
Answer:
D. will not enforce the contract at all because of the change made by Dylan
Explanation:
Answer:
Two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Explanation:
An Israeli physicist named, Eliyahu M. Goldratt developed the Critical Chain Project Management (CCPM) and introduced it in his book "Critical Chain" in 1997.
The CCPM is a project management methodology used by managers to better manage a project. The CCPM ensures that the project plan is feasible and immune from any uncertainty or statistical fluctuations.
In the CCPM activity network, there are no milestones and all non-critical activities are performed as late as possible.
CCPM adopts the use of drum buffers, so as to ensure extra safety is applied to a project immediately before using constrained resource.
According to Goldratt, two activities scheduled to be carried out in parallel and using the same scarce resource are independent.
Answer:
The answer is a the interest rate to fall as there is currently a surplus of loanable funds.
Explanation:
Investors who wish to borrow $100 million represent quantity of money demand and savers who wish to save $125 million. There is surplus of loanable funds SS > DD = $125 million > $100 million