Answer:
B. Information Management
Explanation:
According to Wikipedia, Information management is the collection and management of information from one or more sources and the distribution of that information to one or more audiences.
It is involves collecting, storing and managing information gotten in all its forms. Of course, there are various forms of information, whether physical or electronical or otherwise.
Kristen's Job in the company involves organizing resources info (collecting), regulating how they are used and making sure they are the necessary information needed by the company's workers which is all part of the information management process.
Answer:
E. transportation
Explanation:
The wholesaler is one of the middle-men in the channel of distribution that stands between the producer and the retailer in bulk breaking, he buys in bulk from the producers and sell to the retailer.
One of the functions of the wholesaler in the distribution value chain is the transportation of goods from manufacturer's warehouse to his warehouse at his own cost, thereby bringing the products closer to the consumers.
Complete Question:
You are considering the purchase of a new machine to help produce a new product line being introduced. The machine is expected to have a setup time of 10 minutes per batch and a processing time of 2 minutes per part. You plan to have batch sizes of 50 parts. The plant operates 8 hours per day.
What is the capacity of the machine in batches per day?
Answer:
The capacity of the machine in batches = 4 batches per day.
Explanation:
a) Data and Calculations:
Set up time per batch = 10 minutes
Processing time per part = 2 minutes
Batch sizes = 50 parts
Plant operation = 8 hours per day
b) Capacity in batches per day:
Total batch time = 10 + 50 * 2 = 110 minutes
Total minutes of operation per day = 8 * 60 = 480 minutes
Capacity in batches = 480/110 = 4.36 or approximately 4 batches
c) Each batch produces 50 parts with each part taking some 2 minutes and an additional batch setup time of 10 minutes, giving a total of 110 minutes per batch. Since there are some 480 (8 * 60) minutes available per day, it means that the entity can only run about 4 batches (480/110) per day. These 4 batches will consume a total of 440 minutes (110 x 4), leaving some 40 minutes as unutilized time.