Answer:
52
Step-by-step explanation:
I hope this helps!
Answer: 14
<u>Step-by-step explanation:</u>
Step 1: Graph both equations to find the vertices (see attached):
- The graph shows vertices at: (0, 0), (3, 0), (0, 5) and (2, 3)
Step 2: Input the coordinates of the vertices into the given function (c = 4x + 2y):
- (0, 0): 4(0) + 2(0) = 0
- (3, 0): 4(3) + 2(0) = 12
- (0, 5): 4(0) + 2(5) = 10
- (2, 3): 4(2) + 2(3) = 14
Step 3: Evaluate the value from Step 2 to find the maximum (largest).
- the largest value between {0, 12, 10, 14} is 14
Answer:16.8
Step-by-step explanation: multiply 37 pounds by 0.454 and round
Answer: The probability that the project will be completed in 33 days or less is equal to<u> </u><u>0.73</u> .
Step-by-step explanation:
We assume that this is a normally distribution.
Given : The critical path length is 30 days .
i.e. Population mean = 
Variance : 
Then, standard deviation : 
Z-score : 
The value of z corresponding to 33 = 
Now, the p-value = 
Hence, the probability that the project will be completed in 33 days or less is equal to 0.73.