Wah..I need to ask my bro to answer this.. Brb
Answer:
$78, $79.20
Step-by-step explanation:
PART A: $60 times 1.3 = $78
you add 30% to 100% to get 130% since it is a mark up, and then you convert to a decimal by going to the left twice then multiplying by original price.
PART B
Since it is a discount you subtract 15 percent from 100, but then add back 5 percent since there is tax applied to get 90%, convert to decimal and multiply by original price to get $88 x .9 = $79.20
Answer:
40% . The single reduction together is 40%.
Step-by-step explanation:
Let the bicycle cost is x before reduced price.
First 25% is reduced and again 20% further reduced.
Let the single reduction is y% if the two reduction together are equal.
Solution,
Case .1
reduction cost
%


The cost of bicycle after reduction of 25% is

cost of reduction further reduction of 20%
%


The new cost of bicycle is further reduction of 20% is



Case.2
if single reduction is done new cost of cycle is equal
%=



%
single reduction of a cycle is 40%
Answer is Mary because
8/8 is a whole
4/8 is a half
3/8 is less than 1/2
Answer:
<em>Most likely time, </em>according to PERT (Program evaluation and review technique).
Step-by-step explanation:
PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.
Inside PERT, there are different defined times to accomplished an activity in a project, that is:
- An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
- A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
- A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
- An <em>expected time</em>, an statistical estimation.
Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":
- "[...] in as few as 15 days" is the <em>optimistic time</em>.
- "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
- "[...] but most likely will require 20 days" is the <em>most likely time</em>.
As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.