Answer:
The correct answer is inject cash into it.
Explanation:
Every day, central banks lend money to private banks through auctions. The extraordinary thing about these new liquidity injections starring the European Central Bank or the US Federal Reserve is not so much the operation itself, as the situation in which they occur.
In this case, problems arise when, due to distrust, banks do not lend money to each other, operations that are common when the system is working properly.
With extraordinary placements, the central entities replace that lack of funds that private banks have not been able to obtain from their partners and, at the same time, at a cheaper price - at a lower interest rate.
Answer:
a) November 21, 2013
Explanation:
The expected date of birth (EDB) would be calculated using Naegele's Rule and it is based on a normal 28 days menstrual cycle. The steps are as follows:
First, we need to identify the first day of the last menstrual period (LMP). Then we would count it back to three calendar months from that date. Finally, we would add 1 year and 7 days to that date.
In which case, the first day of LMP is February 14, 2013. Going back three months the date would be November 14, 2012. Finally, when we add 1 year and 7 days it would bring you to November 28, 2013, as the estimated due date.
Answer:
uncertainty avoidance
Explanation:
Based on the information provided within the question it can be said that this is an example of the application of Hofstede's typology under the values which highlight uncertainty avoidance. This term refers to the difference between cultures pertaining to the amount of unpredictability that they can tolerate. Which in this scenario is stating that the Danes have a high tolerance for unpredictability.
Answer:
Please find the detailed answer as follows:
Explanation:
Consider the table attached in the excel.
The above are the requirements of the units of material if demand of 8080 units of S has to be completed.
The requirement of units of U for maintenance is given in the second table.
As the lead time for S is two weeks the components should be ready by the fifth week.
As the lead time for components T and U both is 2 weeks their components should be ready by the third week.
Hence in the first week the required number of units of V, W, Y and Z are to be ordered as all of them are required in the third week.
The required number of units of X are to be ordered in the second week to be ready in third week.
The required units of U, Y and Z are to be ordered considering the requirement to make S plus the maintenance requirements.