Answer:
Instructions are below.
Explanation:
<u>We were provided with the activity rates. To calculate the total cost, first, we need to allocate overhead to both product lines:</u>
<u></u>
Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base
Product K425:
Allocated MOH= (6*80) + (4*100) + (50*1) + (90*1) + (14*1) + (9*80)
Allocated MOH= $1,754
Product M67:
Allocated MOH= (6*500) + (4*1,500) + (50*4) + (90*4) + (14*10) + (9*500)
Allocated MOH= $14,200
<u>Now, we can calculate the unitary cost:</u>
Product K425:
Unitary cost= 13 + 5.6 + (1,754/200)
Unitary cost= $27.37
Product M67:
Unitary cost= 56 + 3.5 + (14,200/2,000)
Unitary cost= $66.6
Answer:
a. enforce the contract or recover what she invested with Finlay.
Explanation:
From the question we are informed about Frank which Through fraudulent means, he induces Ethel to sign a contract to invest with him the profits from her business. In this case When Ethel learns the truth, she may enforce the contract or recover what she invested with Frank. Contract can be regarded as an agreement that exist between two parties which could be private parties to create obligation which is mutual and is enforceable under law, element needed for a contract to be valid is that there must be valid offer as well as acceptance.
<span>The shortest possible time an activity can be completed realistically is called crash time. In project management crash time is a method that is used to shorten the length of a project. To do this, the team will decided on a crucial part of the project they can complete in less time than normal. This speeds up the projects completion time and allows for more work to be completed. </span>
Answer:
Percentage of savings off=45%
Explanation:
Savings=discount×Original item price
First save=(25/100)×179.99=$44.9975
Additional save=(20/100)×179.99=$35.998
Total savings=(44.9975+35.998)=$80.9955
Percentage of savings=(Total saving/Original price)×100
(80.9955/179.99)×100=45%