Answer:
Risks of the project include
disruption in the highway during renovation process. - High risk
Poor material used in the construction - High risk
Rainfall may delay the work process. - Medium risk
Traffic flow management will be difficult during peak hours. - Medium risk
Dust and noise during the construction will disturb the society. - Low risk
Explanation:
The risk register includes Risk description, its impact in terms of probability and measures to mitigate such risk. There are many potential risks that are associated with the construction of the bus shelter. The risks are not acceptable as the highway disruption should be kept to minimum and any delay in the work is not tolerable. These risks are reduced by deploying extra labors so that the renovation work is completed on time.
Answer:
B) $4.67
Explanation:
By definition marginal revenue is the revenue generated by the sale of one more unit of product Z.
Marginal revenue = unit price
Since firm X participates in a perfectly competitive market, it is a price taker, and since the marginal revenue is constant, we can assume that this is the equilibrium price of product Z.
Answer:
40%
Explanation:
tasa de interest simple = (valor final - valor inicial) / valor inicial = ($14 - $10) / $10 = $4 / $10 = 0.4 = 40%
La diferencia entre el interest simple y el interes compuesto es que cuando calculamos interes compuesto, el interes ganado previamente gana mas interest por si solo independiente del capital original. En cambio, con el interest simple, el interest ganado previament no gana interes por cuenta propia.
Answer:
The closest answer is 49.
Explanation:
Given that,
Annual demand, D = 43,000 units
Ordering cost, O = $200
Per unit cost of the item = $50
Annual holding cost, H = annual holding rate × Per unit cost of the item
= 35% × $50
= $17.5


= 991.39
= 992 units
Therefore,
Number of orders per year = Annual demand ÷ EOQ
= 43,000 ÷ 992
= 43.34
Hence, the closest answer is 49 and this is not given in the question.