Answer:
166.25 hours
Explanation:
It take 25 hours if the production is going at 100% capacity, but the production is only going at 67%, therefore, 33% of the capacity is under utilized. It takes 8.25 more hours to finish the unit since the capacity is only at 67%. Finally, it takes 25+8.25 hours to finish a single product, hence taking 166.25 hours for 5 units.
We do this like this:
--> 25 ------ 100
--> X ------ 33
--> 33*25 = 100*X
--> 825/100
--> X=8.25
Hope this clears everything. Thankyou.
The information about the question is incomplete, hence the general answer. It is to be noted that the question is about Gantt Charts.
<h3>What is a Gantt Chart?</h3>
A Gantt Chart is a two-dimensional representation of a project showing the volume of work to be done, how the work is broken down into various parts, how long each part will take, those responsible for each part of the project, and even where each project overlaps.
Gantt chart (sample attached) is very crucial for Project Management. The goal of using a Gantt chart is to ensure that the project is completed on or before the scheduled time in order to prevent losses.
Please note that a Gantt Chart can be created and edited using MS Exel Worksheet.
Learn more about Gantt Chart at:
brainly.com/question/5515485
The aggregate demand curve shows a relationship between aggregate price level and demand at the given spending growth.
<h3>What is demand?</h3>
Demand is explained as the requirement of a certain product in the market, usually this demand is varied if the prices are changed and the demand also is impacted by the supply.
If the prices are high it is highly likely that the demand of that product will reduce if the product is not a necessity.
If the prices are lower the demand for the product will increase.
Learn more about demand and supply at brainly.com/question/27305760
#SPJ1