Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
The answer is letter D. Cognitive Dissonance
Explanation:
When people act contrary to their self-perceptions as reasonable and sensible people, they experience a feeling known as _cognitive dissonance_______.
The correct option is Option A - using credit to pay for purchases.
Answer:
As long as Mitch acted in good faith and tried to make the best possible decision regarding all available information, and his decision was something that any other person could have made, his mistake has to be considered a bad or negative business judgement (business judgement rule). He thought that his actions would benefit the corporation, but he was wrong and the corporation lost money. That types of mistakes are considered normal and just that, mistakes that anyone can make.
In regards with the second issue, that Mitch is a shareholder and a director of a firm that will directly compete with Numero Uno, he must inform the board about this and resign to either Numero Uno or One of a Kind.
Introduction
main body of presentation should include for/against if applicable and an evaluation of the points raised
a conclusion