Answer:
FV= $6,418.20
Explanation:
Giving the following information:
Initial investment (PV)= $5,000
Interest rate (i)= 0.025/12= 0.002083
Number of periods (n)= 10*12= 120 months
<u>To calculate the future value (FV), we need to use the following formula:</u>
FV= PV*(1 + i)^n
FV= 5,000*(1.002083^120)
FV= $6,418.20
Answer:
C) Sales markets of the foreign entity are primarily in foreign countries.
Explanation:
The US dollar is the most commonly used currency in the world, and most of foreign trade is carried out using the US dollar. If the foreign entity sells most of its production overseas (exports) then they will use the US dollar as their functional currency since all their exports will be valued in US dollars.
This is assuming that third party cards refer to third party issued credit cards that are issued by banks while using the credit provider's system. When you get a third party issued card, the information that is always there would be the name, the card number, the card account number, and expiration date (there is also a CVV at the back).
Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
Variance = 0.02141851
Explanation:
We first calculate the mean for the stocks
Mean = (0.1858 - 0.0558 + 0.2081) / 3
Mean = 0.3381 / 3
Mean = 0.1127
Variance = [(0.1858 - 0.1127)^2 + (- 0.0558 - 0.1127)^2 + (0.2081 - 0.1127)^2] / 3 -1
Variance = [0.0731^2 + (-0.1685^2) + 0.0954^2] / 2
Variance = 0.00534361 + 0.02839225 + 0.00910116 / 2
Variance = 0.04283702 / 2
Variance = 0.02141851
The variance of returns is 0.02141851