Answer:
Break-even units = 66.67 units
Explanation:
<em>Break-even point is the level of activity that achieves no profit or loss. At this level profit is zero because the the total revenue is equal to total cost.</em>
<em>The break-even point is calculated as </em>
<em>Units to achieve target profit = (Total general fixed cost for the period + target profit)/ contribution per unit</em>
Contribution per unit = Selling Price - Variable cost
Contribution per unit = 15- (1+3+0.50) = 10.5
Fixed cost = 500 +( 50× 4) = 700
So the units requited to achieve break-even point:
Break-even point = 700/10.5
= 66.67 units
Assume a project has normal cash flows. According to the accept/reject rules, the project should be accepted if the: IRR exceeds the required return.
Internal rate of return (IRR) is a metric used in financial analysis to estimate the potential profitability of an investment. The IRR is the discount rate that drives the net present value (NPV) of all cash flows to zero in discounted cash flow analysts. This suggests that an expected angel investment IRR of at least 22% is considered a good IRR. The higher
the project's projected IRR and the higher the amount above its cost of capital, the more net cash the project brings to the firm. So in this case the project appears to be profitable and management should go ahead with it.
Learn more about IRR here
brainly.com/question/15933534
#SPJ4
Answer:
The correct answer is letter "B": seeks to ensure the future performance of the project work is aligned with the project management plan.
Explanation:
Preventive actions are defined as those that aim to mitigate risks inherent in the operations of a business. Preventive actions lead to entities creating contingency plans that allow them to have certain strategies in front of unexpected situations that could harm the firm's operations.
<em>The project risk management plan is the reference that prevention actions take at the moment of recognizing the set of activities that should be followed to ensure the optimal future performance of a project.</em>
Answer:
A
Explanation:
This seems the most reasonable depending on the interview....if it was for a job then you might need something that is not done with your legs
Explanation:
I dont really know. You can ask the tutors tho.