Answer:
D. $511,920
Explanation:
For determining the estimated manufaturing overhead first determined the predetermined overhead which is shown below:
= (Actual manufacturing overhead - underapplied overhead) ÷ (actual direct labor hours)
= ($506,920 - $23,440) ÷ (20,400 hours)
= $23.7
Now the estimated manufacturing overhead is
= $23.7 × 21,600 hours
= $511,920
Answer:
The correct answer is letter "B": an elaborate timetable.
Explanation:
The main objective of creating a project schedule is to <em>measure and control the amount of time it takes to finish every activity in a project</em>. The project strategy must be provided first describing each step that will be taken to accomplish the company goal to then, based on different metrics, determine how much time those activities will last. Eventually, the project schedule will help to find out when the project will be completed.
They are considered to be functional managers—a functional
manager is those people with authority that are given to them in a way of
controlling a certain department, business or organization, in other words,
they have to manage an organizational unit.