Answer:
Identify the sequence of tasks that take the longest to complete
Explanation:
Program Evaluation and Review Technique (PERT) is a project management tool that is used to manage potential contingencies in the process of executing a project. It is used to schedule ,organize and coordinate tasks in a project.
Determining the critical path on a PERT network lists out the time required for different tasks to be completed and as a result , the sequence of tasks that require the longest time are identified.
Answer:
D $88410
Explanation:
Work in progress includes all the raw materials, direct labour and conversion costs incurred so far excluding cost of goods sold .
WIP= Intial WIP +Manufacturing costs incurred- Cost of goods sold.
The WIP inventory at the begining of the period is given as nil.
WIP during the period = (95000*80%)+56000+13600+107000
=252600(but it was given that 65% of the Process was completedi.e., finished goodswhich are not the part of the WIP inventory ; hence the remaining 35% is the Work in process inventory)
=$ 88410.
Further the remaining raw material 20% = 95000*20% shall not comprise a part of the WIP as it has not been brought into process itself , it shall lie in raw materials inventory itself.It shall be counted into the WIP once it is brought into the manufacturing assembly line.
Answer:
Variable cost per unit= $1.4 per unit
Explanation:
Giving the following information:
Miles Driven Total Cost Miles Driven Total Cost
January: 8,000 $14,120
March: 8,550 $14,979
February: 7,490 $13,495
April: 8,195 $14,490
To calculate the variable cost under the high-low method, we need to use the following formula:
Variable cost per unit= (Highest activity cost - Lowest activity cost)/ (Highest activity units - Lowest activity units)
Variable cost per unit= (14,979 - 13,495) / (8,550 - 7,490)
Variable cost per unit= $1.4 per unit
Answer:
b. New brands require higher spending to reach a minimum level of exposure needed to affect purchase habits
Explanation:
New brands with a small market share tend to spend proportionately more for advertising and sales promotion than those with a large market share because a certain minimum level of exposure is needed to measurably affect purchase habits.
Answer:
A: $1,475,000
Explanation:
The computation of the overhead applied is shown below:
But before that first determine the predetermined overhead rate which is
= Estimated annual overhead cost ÷ Estimated machine hours
= $1,500,000 ÷ 300,000
= $5
Now the applied overhead is
= Predetermined overhead rate × Actual machine hours
= $5 × 295,000
= $1,475,000