A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the criti
cal path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete?
1 answer:
Answer:
Step-by-step explanation:
What is given:
Formula to be used Z = (X - mean) / standard deviation
Mean = 214
X = 224
Variance = 100
Formula of Standard deviation = sqrt(variance) = sqrt(100) = 10
So Z = (224 - 214) / 10 = 10/10 = 1
For z = 1, the probability is 0.3413; 34.13% ⇒ The probability of project being completed by 224 days is 34.13%
You might be interested in
The answers are right! Good job!
race entry costs 55, they use 15 of it to cover costs so they get 55-15 = 40 per entry
x = race entries
equation becomes 55000>= 40x +10000
45000>= 40x
x >= 45000/40 >= 1125
they need at least 1125 race entries to make $55,000
Answer:
Step-by-step explanation:
3x + -3x - 4y = 8 - 3x
-4y = 8 - 3x
-----------------
-4
y = 8/-4 + 3/4 x
y = -2 + 3/4x
Answer:
c>5
Step-by-step explanation:
Answer:
16 outcomes
Step-by-step explanation:
4 outcomes for spinner
2 outcomes for 1st coin
2 outcomes for 2nd coin
4 x 2 x 2 = 16