Answer:
The correct option is A
Explanation:
In project management, earliest finish time for activity A refers to the earliest start time for succeeding activities such as B and C to start.
Assume that activities A and B comes before C, the earliest finish time for C can be arrived at by computing the earliest start-finish (critical path) of the activity with the largest EF.
That is, if two activities (A and B) come before activity C, one can estimate how long it's going to take to complete activity C if ones knows how long activity B will take (being the activity with the largest earliest finish time).
Cheers!
Answer:
b. ethernet
Explanation:
It was an ethernet that was developed in the 1970s that improved the ability to send the information over the network. It is the most widely used method to connect the computers in a LAN or the local area network, ever since 1980 when it was first introduced for commercial use. And it is being used in bulk even today.
1)How many memory cards (how many can you computer hold)
2)Company (some companies run better than others)
3)Amount of memory (xGb)
The process is called booting