The minimal completion time for the activities is the shortest possible time for all the activities to be finished. In doing this, we look at the path that would require the greatest amount of time. At the START node, we choose the path that would take the longest which is 7 days leading to ACTIVITY D. Next, we choose the path leading to ACTIVITY B which takes 5 days. Then, we move to ACTIVITY C taking 5 days and finally, reach the END which would take 6 days. So, the minimal completion time is:
7 + 5 + 5 + 6 = 23 days
39 miles. If d=rt and the rate is 16 mph and the time is 3 hours then 16 times 3 gives the distance of 39 miles. I could be wrong but that is what I would have done. I’m not sure if there are answer choices or not
Answer:
C. (5, -3)
Step-by-step explanation:
Ordered pair just means the coordinate or the point at which both of the graphs intersect. On the x-axis, this is at point 5, and on the y-axis, this is at point -3. Since an ordered pair is in the form (x, y), the answer is therefore C.
Answer:
5
Step-by-step explanation:
Put -2 where x is and do the arithmetic.
f(x) = 2x² -3
f(-2) = 2(-2)² -3 = 2(-2)(-2) -3 = 8 -3
f(-2) = 5
Answer:
Step-by-step explanation:
let x = the amount of money in the second piggy back
We assume that the second piggy bank has MORE than the piggy bank with $7.31 in it:
x - 7.31 ≤ 10
<u>Solution</u>
Add 7.31 to both sides: x - 7.31 + 7.31 ≤ 10 + 7.31
⇒ x ≤ 17.31