Answer:
c) Adding additional project resources to the project
Explanation:
Falling behind schedule is something that needs to be avoided or dealt with promptly and systematically
Crashing is the technique to use when fast tracking has not saved enough time on the project schedule. You use crashing to save resources to the project for the least cost possible. Anyhow, crashing is expensive because more resources are added to the project.
References:
Dave. “A Step-by-Step Process of Dealing with a Project That Is Falling behind Schedule.” MyClientSpot Blog, 10 Sept. 2015
Monnappa, Avantika. “Project Management Learning Series: Fast Tracking Versus Crashing.” Simplilearn.com, Simplilearn, 27 Sept. 2019,
Answer: True
Explanation: By conducting a small project as a proposal, a contractor is actually showing in a small scale that he is both capable, is the right man for the job (external project) and is able to ensure the external project is completed with its goals and objectives accomplished. It is these goals that drive the project, and all the planning and implementation . As such, the project has to be compelling and complete.
True gives the answer to the question.
The answer is project. <span>In a matrix organization, each employee reports to a functional and a(n) project manager. you can look it up on quizlet.</span>
Answer: $828
Explanation:
Given the following :
Semi-annual payment = $40
Period = 20 years
Number of payments = (20 * 2)(semiannual) = 40 payments
Par value = $1000
Interest rate = 5%
Using the PV table:
PV at $1 (40, 5%) = 0.1420
PVA at $1 (40, 5%) = 17.159
[Par value * PV at $1 (40, 5%)] + [$40 * PVA at $1 (40, 5%)]
= ($1000 * 0.1420) + ($40 * 17.159)
= $142 + $686.36
=$828.36
= $826