Answer:
The correct answer is the second option: to monitor the progress of a multi-step project during its development.
Explanation:
To begin with, a <em>"Program Evaluation and Reviews Techniques"</em> or PERT as it name indicates it refers to an stadistic technique by which the companies can follow the process of certain projects that they are having currently. Moreover, its main purpose is to manage and analyze the steps that a project has in order to make them less susceptible to errors. In addition to that, its main factor to observe is the time during the steps of the project. Nowadays is very common to use a tool like this in major companies.
Answer:
1.89%
Explanation:
The book value of the merchandise is $178,000
Physical inventory reveals stock is worth $169,000
The shrinkage = $178,000 - $169,000
=$9000
As a percentage of sales, the shrinkage will be
=$9000/$476,000 x 100
=0.0189076 x 100
=1.89%
Answer:
The correct answer is the option A: a person with a high opportunity cost of time.
Explanation:
To begin with, the opportunity cost of something is what the person sacrificies in order to be doing that thing. Therefore that when we talk about the opportunity cost of time it refers to what the person sacrificies in order to do something with that time. If the person has a high opportunity cost of time then the sacrificies that he made with that time will be higher than other person that has a low opportunity cost of time, meaning that the time spent by that person is less important than to the one that has a lot of time to spare.
The correct answer is all of the above. Multinational corporations grapple with a diversity of challenges when choosing training programs for their employees. These include choosing a program that is sensitive to the local culture and how to reconcile it with the global nature of the corporation. This also introduces the challenge of who should conduct the training.
Answer:
B) average total cost must be rising
Explanation:
Marginal cost is the rate at which total variable cost increases when one more unit is produces.
So when marginal cost is larger than average cost, it means that total average costs must be increasing.
For example, we have the following production costs:
- total costs = $100
- units produced = 20 units
- total average costs = $5 per unit
If the marginal cost of producing 1 more unit is $6, then the total costs will be $106 and the total average cost will be $5.05 per unit (= $106 / 21 units).