1answer.
Ask question
Login Signup
Ask question
All categories
  • English
  • Mathematics
  • Social Studies
  • Business
  • History
  • Health
  • Geography
  • Biology
  • Physics
  • Chemistry
  • Computers and Technology
  • Arts
  • World Languages
  • Spanish
  • French
  • German
  • Advanced Placement (AP)
  • SAT
  • Medicine
  • Law
  • Engineering
Gnom [1K]
3 years ago
11

A car rents for $45 per day plus .22cent toy are on a daily budget of 77 what mialage

Mathematics
1 answer:
elena55 [62]3 years ago
4 0
If its $45 per day plus $0.22 cents, and you only have $77. You can only have the car for 1.7 days which adds up too $76.94.
You might be interested in
What is 975, 462 round to the nearest hundred thousand
podryga [215]

Answer:

it would be 1 million, ( 1,000,000 )

Step-by-step explanation:

1.) look to the right of the nine , (7)

2.) 7 is greater than five therefore rounding it up to 1,000,000

5 0
3 years ago
What’s the answer to this question?
steposvetlana [31]

Answer:

its x^4

Step-by-step explanation:

its x^4

5 0
3 years ago
PLSSS HELP MY TEST IS ALMOST OVER
Ipatiy [6.2K]
I think the answer is b
8 0
3 years ago
(temperature) answer answer answer answer answer answer answer answer answer answer answer
Bond [772]

Answer:

100

Step-by-step explanation:

8 0
3 years ago
Read 2 more answers
mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days
4vir4ik [10]

Answer:

<em>Most likely time, </em>according to PERT (Program evaluation and review technique).

Step-by-step explanation:

PERT is "a statistical tool used in <em>project management" (Program evaluation and review technique (2020), </em>in Wikipedia), and it is commonly used with CPM <em>(Critical Path Method)</em> to manage projects.

Inside PERT, there are different defined times to accomplished an activity in a project, that is:

  • An <em>optimistic time</em> or minimum time required to accomplished an activity, i.e., if everything goes better than normal, the activity is accomplished before expected.
  • A <em>pessimistic time, </em>a time quite the opposite to optimistic time.
  • A <em>most likely time</em>, or a time required to accomplished an activity if everything goes as expected or normally.
  • An <em>expected time</em>, an statistical estimation.

Considering the question, we have that the <em>time</em> when "the first module of the project could be completed":

  • "[...] in as few as 15 days"  is the <em>optimistic time</em>.
  • "[...] or could take as many as 25 days" is the <em>pessimistic time</em>.
  • "[...] but most likely will require 20 days" is the <em>most likely time</em>.

As a result, the <em>20-day estimate</em> is called the <em>most likely time</em> in the context of the PERT/CPM techniques.

3 0
3 years ago
Other questions:
  • Is square root 72 rational or irrational explain
    8·1 answer
  • Jeff finds some bugs. he finds 10 fewer grasshopper than ladybugs. if jeff finds 5 grasshoppers how many lady bugs does jeff fin
    6·1 answer
  • Simplify (-5t^2+6t-7) + (3t^2+t+4)
    7·1 answer
  • X+5y; use x = 1 5/6, and y = 3 1/6
    10·1 answer
  • The data set gives the number of hours it took each of the 10 students in a cooking class to master a particular technique.
    15·2 answers
  • Given the equation y = 7 sec(6x– 30)<br><br> The period is:<br><br> The horizontal shift is:
    12·1 answer
  • What is the mean for 46 47 52 55 64 69 70 78
    11·1 answer
  • 2. Find the area; reduce to lowest terms:<br> Length: 2 3/4 feet width 2/5 feet
    15·1 answer
  • Write an equation based on the table below
    11·1 answer
  • Directions: Convert each measurement. <br> 1. 20 ounces = __________ lbs __________ oz
    10·1 answer
Add answer
Login
Not registered? Fast signup
Signup
Login Signup
Ask question!