Answer:
(2). Inventory issues
Explanation:
Chase strategy for aggregate planning are usually used by organization as a way of reducing cost and managing inventory related issues. Inventory issues can be managed internally by increasing stock during periods of slack demand and same can be used to service stock during periods of high demands.
Organizational cost is effectively managed, as workers contribute productively at all periods to the bottom line.
Answer:
14,275= actual hours
Explanation:
Giving the following information:
The standard for a particular crane calls for 14 direct labor-hours at $16 per direct labor-hour.
During a recent period, 1,000 cranes were made.
The labor efficiency variance was $4,400 Unfavorable.
To determine the actual hours worked, we need to use the direct labor efficiency variance formula:
Direct labor time (efficiency) variance= (Standard Quantity - Actual Quantity)*standard rate
-4,400= (14*1,000 - actual hours)*16
-4,400= 224,000 - 16actual hours
228,400/16= actual hours
14,275= actual hours
The output of mosquito reppelent is a toxin that is harmful to mosquitos