Answer:
Fourth option: 30 days
Step-by-step explanation:
We three path to complete the project:
Path A:
A1 → A2 → A3
10 days → 8 days → 9 days = 27 days
Path B:
B1 → B2 → B3
2 days → 7 days → 3 days = 12 days
Path C:
C1 → C2 → C3
10 days → 8 days → 12 days = 30 days
Then the duration of the critical path is 30 days, we can't conclude the project until each path has finished
Answer:
-7/6
Step-by-step explanation:
The slope formula can be used with any pair of points.
m = (y2 -y1)/(x2 -x1)
m = (1 -8)/(-2 -(-8)) = -7/6
The slope of the line is -7/6.
Answer: X-3(2x-8)= -25
A. X= 11
B. X= 14
C. X=10
D. x=5
Step-by-step explanation:
Answer:
The only fraction i can think of is 2/9
Step-by-step explanation:
well, we know is 10% for the first 7500, but Dan only made 5000 of taxable income, so he's in that range of 0 - 7500, so he only gets to pay 10% of 5000.
