The approach that Mr. McKay is using in the setting is the
problem based learning. The PBL or the Problem based learning is defined as a
student centered pedagogy by which students are likely to learn a particular subject
based from the experience of having to solve open ended problem found in a
material that triggers it.
Answer:
Total Equivalent Units Conversion 746,000
Explanation:
Breakfast Cereal Maker
Weighted-Average Inventory Method
Total Equivalent Units
Units Conversion Equivalent Units
Particulars %
Units completed 620,000 100 % 620,000
<u>Add Ending WIP 180,000 70 % 126,000</u>
<u>Total Equivalent Units 746,000</u>
<u />
<em>The total Equivalent units are obtained by adding the percent of the units in the ending work in process inventory to the units completed and transferred out. This is the average weighted method of finding the equivalent units.</em>
<em>As only conversion is required we found out the conversion units only.</em>
Answer:
A. A balance sheet shows the total assets, liabilities, and owner's
equity at the end of the period
Explanation:
As we know that
The income statement recognized only the income earned and expenses incurred of an organization
While on the other hand the balance sheet shows the financial position, profitability of the company. It involves assets, liabilities and stockholder equity
So according to the given options, the option A is correct
hence, the rest of the options would be incorrect
Answer:
NPV = $20,040.35
Explanation
The net present value NPV) of a project is the present value of cash inflow less the present value of cash outflow of the project.
NPV = PV of cash inflow - PV of cash outflow
We can set out the cash flows of the project using the table below:
Annual net cash inflow = Savings - Technician cost = 61,427- 20,000
= $41,427
PV of Cash flow= $41,427 × (1-(1.12^(-5))/0.12= 149,335.06
PV of salvage value = 1.12^(-5)×$6,641 = 3768.281749
NPV = 149,335.06 + 3,768.281 -133,063= 20,040.35