Answer:
The Atlanta's cost allocated to Nashville will be $663,500.
Explanation:
Administration: $700,000 x 80% = $560,000
Legal: $138,000 x [18,000 ÷ (18,000 + 6,000)] = $103,500
Solution: $560,000 + $103,500 = $663,500.
Forecasting is like Foreshadowing telling or predicting what may happen.
it could not be B Because you already have your budget because, without a budget you can not go forth with your plans.
C is not because, it is potential you should calculate it but, altogether is not in your revenue which is something that comes altogether but, this is just a part of the full revenue.
And D. This is something specific you cannot just pay attention to not just expenses but what you earn, what budget and etc.
Altogether leaving A because, you are gathering information and does not tell you what type but, financial which means 'all' activities of Financing and Planning will help with Revenue to protect it and, to get it to the point in which you want it to get to a goal or past a goal and etc.
Answer:
Direct labor cost= $31,200
Explanation:
Giving the following information:
Production= 48,000 units
Standard time= 3 minutes per unit
Rate= $13 per hour
First, we need to calculate the number of hours required:
The proportion of minuted per hour= 3/60= 0.05
Number of hours= 48,000*0.05= 2,400 hours
Now, the direct labor cost:
Direct labor cost= 2,400*13= $31,200
Answer:
The correct answer is letter "A": Joanna, who is firm and dependable with respect to delivering results.
Explanation:
Operational leaders are those who analyze the strengths and weaknesses of their group to allocate the duties in a way that produces the most efficient outcome. In front of problems, this type of leader studies the impact and what is going to be needed to solve it. Operational leaders are mostly <em>results-driven</em>.
Answer:
$12.53
Explanation:
Data provided in the question
Par value = $1,000
Coupon rate = 2.5%
Reference CPI = 204.89
Now CPI = 205.44
By considering the above information, the correct calculation of the current interest payment is
= Par value × Current CPI ÷ Reference CPI × Coupon rate ÷ 2
= $1,000 × 205.44 ÷ 204.89 × 2.5% ÷ 2
= $12.53
We assume the interest is on semi annual payments