Answer:
Anahdbd8enduemahehnwkh2vehnsnbvcjuygvvnic
Hinde ko po talaga alam
Step-by-step explanation:
Bcbvcujrirjrhjd26yehfnx
Sorry po talaga
Answer:
4.74 hours
Step-by-step explanation:
Given that both person have to place same number of rivets that is
11209
first person take 9 hours to complete the work
hence 1 hour work of 1st person is
of total work
second person takes 10 hours to complete the same work
hence 1 hour work of 2nd person is 
Now if both work together then
1 hour work of both person =
=
thus working together they need
hours = 4.74 hours to complete the whole work which is placing 11209 rivets
Answer:
Between 3 and 4
Step-by-step explanation:
Since .68 is 68/100, you can simplify to 17/25.
That would be 1+y≥9
the one and the y go on one side and the nine on the other