Standard deviations of the four activities of the critical path are 1,2,4,2.
Standard deviation of this critical path = Sum of square root of variance of this corresponding critical path
Standard deviation of critical path
Now we need to find the probability that the project will completed in 38 weeks given that its expected completion time is 40 weeks.
That is, we need to find P(X<38) :
Probability
Thus the probability that the project will be completed in 38 weeks is 0.34.
A.
If:
j - the price of a glass of juice
p - the price of a pancake special
Then:
3j + 5p = 7.60
j + 2p = 2.90
b.
If:
j + 2p = 2.90
Then:
j = 2.90 - 2p
We can substite j in the first equation.
<span>If:
3j + 5p = 7.60
</span><span>j = 2.90 - 2p
</span>Then:
3×(2.90-2p) + 5p = 7.60
8.70 - 6p + 5p = 7.60
8.70 - p = 7.60
⇒ p = 8.70 - 7.60
⇒ p = 1.10
If:
<span>j = 2.90 - 2p
</span><span>p = 1.10
</span>Then:
j = 2.90 - 2×1.10
j = 2.90 - 2.20
j = 0.70
Thus, the price of a glass of juice is $0.70 and <span>the price of a pancake special is $1.10.
c.
If:
p = 1.10
j = 0.70
Then:
j + p = 1.10 + 0.70 = 1.80
Thus, </span><span>the bill for 1 glass of orange juice and 1 pancake special is $1.80.</span>
$122.4384 is the answer...it is found by multiplying .04% to 127.54 and then subtracting that answer from the original ammount
Answer:
5*4*4=80
Step-by-step explanation:
brainliest?
Answer: 0.22kg
Step-by-step explanation:
if she has 3 kg then she has 3000 g. 3220-3000=220 So she needs 220 more grams of titanium. If she needs to convert how much more from grams to kilograms then 220g= 0.22kg so she needs 0.22 kg more
To check work
3kg+0.22kg= 3.22kg
3.22kg= 3,220g