Answer:
- Project completion time: 21 weeks
- Critical Path: B - E - G
- ES, EF, LS, LF are shown below
Explanation:
The earliest start is the latest of the earliest finish times of the predecessors. The earliest finish is the sum of earliest start and duration.
The latest finish is the earliest of the latest start times of the successors. The latest start is the difference of latest finish and duration.
The slack is the difference between earliest start (or finish) and latest start (or finish).
Project duration is the earliest start of the "Project Done" task. For purposes of computing slack, this (project duration) is taken to be the latest finish of the immediate predecessors.
The critical path is the sequence of tasks with 0 slack.
Answer:
C. Debit Work in Process—Dept. B; credit Finished Goods—Dept. A
Explanation:
It is known that during continuous production, businesses find it difficult to isolate each individual unit and calculate a cost. Process costing systems accumulate the materials, labor and overhead costs for the period along with the total number of units produced. The total number of units produced includes both completed units and partially completed units. The company determines the percentage of completion for each partially completed unit and adds these amounts to the total number of completed units to determine the equivalent units.
Answer:
C. Increase
Explanation:
A bustling economy will make individuals want to take advantage of the opportunity. It’s however normal for prices of a good or service to increase when there is a huge demand for it.
In this case there was a boom in the economy which means the price of the shares he owns in the company will increase.
Answer:
false
Explanation:
The allowance procedure estimates bad debt expense before an uncollectible account receivable has been purposed to be uncollectible.
Answer:
The person receiving the order should read it back to ensure that the order is correct.
Explanation:
In business communication the best way to communicate orders is in written form since this allows for clear conveyance of the message in the order. Using verbal means to give orders over the phone is prone to misinterpretation and there is less accountability when the subordinate claims he did not understand the order.
To curtail this it is advisable for the recipient of the order to repeat the order. This shows it has been clearly understood.