Answer:
a. (AR-SR)* Actual hours = Labour rate variance
Actual rate = (-3,850/2,750) + $17.60
Actual rate = -$1.4 + $17.60
Actual rate = $16.20
b. Direct labour efficiency variance for August = Total direct labour budget variance - Direct labour rate variance
= 1,430 - (-$3,850)
= $5280 Unfavourable
c. Direct Labour efficiency variance = (AH-SH)*SR
5280 = (2,750 - SH) * 17.60
(2,750 - Standard hours) = 5280/17.60
(2,750 - Standard hours) = 300
Standard hours = 2,750 - 300
Standard hours = 2,450
Answer:
Tab + windows
Explanation:
I got it right in the 2nd try EDGE2020
Division of lab our is the same thing as Specialization.
Answer:
(a). For every additional square foot of area of a house, the price is predicted to increase by $61
(b) The asking price is $145410 and the residual is a negative $4100
Explanation:
As per the data given in the question,
a) From regression equation Slope = 0.061
So slope = (0.061 × 1,000) ÷ 1 sq. ft.
= $61 per sq. ft.
For every additional square foot area price is increased by $61
b) If size of the house is = 1600 square foot then
Price = 47.81 + 1600*0.061
=$145,410
The asked price is $4,100 less than estimated price and residual is not positive
Hence,
Asking price = $145,410
Residual price = a negative $4,100