Ram can complete the work in 10 hours, Ajit in 12 hours and Suresh in 15 hours. All of them began the work together, but Ram had
to leave the work after 2 hours of the start and Ajit left 3 hours before the completion of the work. How long did the work last? Select one: a. 7 hrs
b. 8 hrs
c. 9 hrs
d. Cannot be determined
D. Because Ram only did 2 hours so then that makes 2 hours of work done but then left for whatever reason. Ajit left 3 hours BEFORE the completion of the work and that gives us info that there were hours put in between both Rams and Ajits work. They all started at the same time so it doesn't mean that Ajit didn't do any of the work. Ajit can work for 12 hours POSSIBLY. It did not say he can exact. So it leaves to Suresh that can work up to 15 hours of the work but we dont know how long he did it. Suresh either could just gone over or less than 15 hours.
If this answer was way out of the question then i am sorry and i probably was wrong.
I was just asking for her phone number so i can we go watch her video of the video she can see it in my video i i said yeah oh gosh gosh i yeah oh yeah yeah oh gosh gosh i yeah oh gosh oh wow oh yeah that’s why