Answer:
They offer shares and release their company on the stock market to be publicly traded.
Explanation:
Answer:
$3200 favorable
Explanation:
We have given range of number of production = 40000 units
So average of number of units 
Variable cost = $2 per unit
So total variable cost = 40000×$2 = $80000
Fixed overhead = $72000
Budgeted overhead for actual production = Variable overhead +Fixed overhead = $80000+$72000 = $152000
Actual total overhead cost = $148,800
Total overhead controllable cost variance = Budgeted overhead - Actual overhead
= $152,000 - $148,800 = $3,200 favorable.
Answer:
a. The socially efficient levels of abatement for UNC power plant is 10.
Explanation:
Note: See the attached Microsoft word file for the calculations of the anwers above.
Answer:
Sunk cost
Explanation:
The sunken cost is the expense previously incurred that will not be compensated in future. Plus, it's also called past expense.
The cost at the time of decision-making is not significant and it should be ignored.
In the given question, the $3,500 spent which is not now recovered and hence represents the sunk cost
Answer:
Instructions are below.
Explanation:
Giving the following information:
Total fixed costs= 300,000
Total costs= $450,000
Units= 120,000
A) Unitary variable cost= 150,000/120,000= $1.25
B) Units= 75,000
<u>The fixed costs remain constant no matter how many units are made (between relevant ranges).</u>
Total fixed costs= $300,000
C) UNits= 160,000
Total variable costs= 1.25*160,000= $200,000
D) Units= 180,000
Total fixed costs= 300,000
Total variable costs= 1.25*180,0000= 225,000
Total costs= $525,000