Answer:
Total Cost per square footage= $ 119.76
Explanation:
<em>As each of these costs is related to the area and building the cost driver would be area square footage floor space.</em>
<em>We divide the cost with the cost driver to get the parametric cost estimate for each of the following.</em>
a.Concrete parking deck cost $5,250,000 / 150,000 sf floor space=$35 per sf floor space
b.Concrete warehouse cost $1,680,000 / 80,000 sf floor space= 21 per sf floor space
c.Non post tensioned concrete parking deck cost $5,400,000 /200,000 sf floor space= 27 per sf floor space
d.Post tensioned Concrete parking deck cost $6,250,000 / 170,000 sf floor space= 36.76 per sf floor space
Total Cost per square footage= $35+ $21+ $27+ $36.76= $ 119.76