Answer:
b. is zero.
Explanation:
Taxation can be defined as the involuntary or compulsory fees levied on individuals or business entities by the government to generate revenues used for funding public institutions and activities.
There are three (3) types of taxation used by the government, these are;
1. Progressive taxation: it involves charging individuals having higher incomes a higher percentage of their total income.
For instance, Citizen A pays 20% on $50,000 and Citizen B pays 15% on $36.000.
2. Proportional taxation: it involves charging both lower and higher income earners equally in proportion to their income.
For instance, Citizen A pays 10% on $50,000 and Citizen B pays 10% on $36,000.
3. Regressive taxation: it involves charging individuals with low incomes a higher percentage of their total income and vice-versa.
For instance, Citizen A pays 15% on $50,000 and Citizen B pays 20% on $36,000.
The marginal tax rate for a lump-sum tax is zero because an additional amount of money would not change it.
Answer:
A. 1 week
Explanation:
This is true due to the fact that, Cassandra knew it would take about 1 week to establish the price point in the new product which she is planning to launch.
For the extra week it would have taken to get the paper could not hold again due to the fact that, it was already established that, it would take same day to get same paper rather than waiting for the paper to get to the strategy group in one week.
Answer:
YNW's ah family YNW's ah family
Explanation:
Correct answer choice is:
D. April 30
Explanation:
The billing cycle for a credit card or whatever sort of cyclical account is the duration of time connecting billings. For instance, a billing cycle may begin on the 1st day of the month and finishes on the 30th day of the month. Or, it may proceed of the 15th of an individual month to the 15th of the following month.
Answer:
The correct answer is (a)- Parallel teams.
Explanation:
The majority of the teams in which the manager or boss assigns and directs the work of the team, normally what we see is the so-called "parallel work" in which each team member develops only one functionality planned in the scope of the project . This type of organization gives the administrator the feeling that several of the functionalities are being developed at the same time, which should ensure that the project is not delayed. Well, if we analyze this with a little more care we will see that what happens is exactly the opposite.