Complete Question:
The project represented by this resource load chart (see attached) has a maximum limit of 6 units of resource activity in any day. The first activities that are strong candidates for shifting are:
A) Activity A
B) Activities B and C
C) Activities D and E
D) Activity E and F
Answer:
The first activities that are strong candidates for shifting are:
C) Activities D and E
Explanation:
Activities D and E have a total time of 5 days altogether based on the attached resource load chart. They have the least time and can be shifted to accommodate other activities before they can be tackled sequentially.
A resource load chart displays the total amount of resources required as a function of time in any given project. It is the best method for establishing the existence of some resource conflicts across project activities, especially when compared to Gantt Charts, Network Diagrams, and Pareto Diagrams.
Answer:
The correct option is D
Explanation:
Under the method of allowance, the uncollectible accounts receivable will be recorded in the same accounting period as the sale of an estimate of the bad debt expense. So, the collection of the account which was earlier written off, will not have any affect on the income in the period or year it is received or collected.
I think the answer is the first one: Tina recognizes that there is a fundamental flaw in her approach to the plans for a project, and revises them to better align with the clients vision.
Answer:
D. overcome the fear of being alone in a hostile world
Explanation: