Shrink nations work force
Answer:
False
Explanation:
The statement that says that in the context of project management, a task duration is always the same as the amount of work (effort) it takes to finish the task is false because the effort is the time a person needs to finish a task while the duration is the period of time that a person has to finish it. For example, an employee has a task that takes forty hours of work to finish it but he has a month to do it. In this case, the effort is forty hours but the task duration is one month.
Answer:
The required return for the new project is 6.87%
Explanation:
In order to calculate the required return for the new project we would have to calculate the Weighted Average Cost of Capital (WACC) adjusted by risk adjustment factor
.
The Weighted Average Cost of Capital (WACC) = [After Tax Cost of Debt x Weight of Debt] + [Cost of equity x Weight of Equity]
After -tax Cost of Debt = 3.40%
Cost of Equity = 10.80%
Weight of Debt = 0.39
Weight of Equity = 0.69
Therefore, the Weighted Average Cost of Capital (WACC) = [After Tax Cost of Debt x Weight of Debt] + [Cost of equity x Weight of Equity]
= [3.40% x 0.39] + [10.80% x 0.69]
= 1.32% + 7.45%
= 8.77%
The required return for the new project = Weighted Average Cost of Capital – Risk Adjustment Factor
= 8.77% - 1.90%
= 6.87%
The required return for the new project is 6.87%
First Identity the primary activities
Then goes select an allocation
Followed by calculating an activity
And finally allocate the costs
Hope this helps