<span>Refer to standard motor products. when standard motor products’ edwardsville plant decided to give its teams the highest level of autonomy, it created self-designing teams. A self-designing team is a team that decides who they want to work with, how they want to work together and what they want to work on. This has been shown to create productivity because these workers are happy with the work they are </span>doing and making decisions instead of being just told what to do.
Answer: $30
Explanation:
Given that,
Average variable cost (AVC) = $25
Average fixed cost (AFC) = $5
Marginal cost (MC) = $30
Average total cost (ATC) = Average fixed cost (AFC) + Average variable cost (AVC)
= $5 + $25
= $30
Therefore, average total cost is the sum of average fixed cost and average variable cost. Alternatively, average total cost is calculated by dividing total cost to units of output produced.
Answer: C) $2,000 per week.
Explanation:
The slope of the project refers to the additional amount that it would cost to be able to finish the project faster than schedule.
In the question, the construction activity is for 14 weeks at a rate of $5,000 for the laborers per week. If you wanted to reduce this project duration to 10 weeks, you will have to spend an additional $2,000 more per week.
This $2,000 is therefore the slope of the activity.
Answer:
Cash payments for income tax = $165000
so correct option is C. 165,000
Explanation:
given data
Income tax = $175,000
beginning tax payable = $30,000
end of the year tax payable = $40,000
to find out
Cash payments for income tax reported on the statement of cash flows
solution
we get here Cash payments for income tax that is express as
Cash payments for income tax = Income tax + beginning tax payable - end of the year tax payable ..............................1
put here value we get
Cash payments for income tax = $175000 + $30000 - $40000
Cash payments for income tax = $165000
so correct option is C. 165,000